K+S Potash

8000 tons, 2016

This $4.1 billion Legacy green field mega-project is the first new potash mine in Saskatchewan in over 40 years. The project was commissioned in 2016. The scope of this project included the main process buildings, which comprise nine major industrial structures. In addition to the steel structure, the project included rough-setting approximately 515 pieces of equipment and ninety large pipe/electrical modules. Our scope consisting of four buildings weighing 8000 tons, was received in July 2014 and completed in 6 months, including 15% change orders. These equipment support structures typically included main steel, complex miscellaneous steel, Handrails, Stairs, Cage ladders, Safety gates, Removable gates, Checker plates, etc. All connections were fatigue-critical connections and therefore exceptional care had to be taken to meet this requirement.